My experience with projects and AP in general. ~$2mm across 70 liens without any split between contractors vs spacex is not that interesting. Did not look like they even accounted for a chain of liens based on the same original unit of work. The report came out in 2024 and the count and $ sum was from 2019, so over 5 years including COVID years. During COVID liens jumped quite a bit and on projects that span multiple years I don't find $2mm over 5 years that shocking.

Now SpaceX could totally be stretching their NWC as far as it goes and always paying late on purpose. Really impossible to tell in this style of shock reporting.

I would be surprised in your experience that you have never had cases of a GC not paying on his end and those folks throwing a <$100k lien on the project. Or a dispute between the GC and payer.



There are disputes about payment on lots of projects I've worked on. That wasn't your claim. You claimed that liens were filed and perfected on "most" jobs, and that is not my experience.


And I said that was my experience that liens often crop up and the scale of these were not out of the norm especially on the project size and timeline. After all the project is actively being used and some of these are not purely new construction related. Boo.